Acton Storm Tanks

Site information

Acton Storm Tanks

Relining of Sewer and Interception Chamber Excavation
On 23 and 24 April we will be carrying out overnight work on the sewer. On 23 April, during the day, we will be working on the interception chamber.

Water Monitoring
As we progress with the excavation for the drop shaft, we need to monitor the water network pipes that runs adjacent to the Acton Storm Tanks site, to ensure that there are no leakages in the system.

The site will be closed for the Easter break from Friday 19 April and will reopen on Tuesday 23 April.

Our standard working hours are (with a 1-hour mobilisation period before and after these times):

  • Monday – Friday: 8am – 6pm

  • Saturday: 8am – 12 midday

Additionally, we have maintenance periods on the weekend:

  • Saturday: 1 – 5pm

  • Sunday: 10am – 4pm

We will be working 24-hours a day for approximately seven months. This is be taking place predominantly underground as we construct our tunnel.

On average, we have approximately seven heavy goods vehicles accessing the site. More up to date information about the vehicle movements can be found within the CLWG presentations.

The next Acton Storm Tanks CLWG will be held on Monday 21 May 2019, 7-9pm, at the 14th Acton Scout Group, Rugby Road, Chiswick, London W4 1AT.

You can see the the minutes and presentation from the last CLWG below. If you are interested in finding out more about our community liaison working group please email [email protected]

11 February 2019 - CLWG Minutes
11 February 2019 - CLWG Presentation

11 September 2018 - CLWG Minutes
11 September 2018 - CLWG Presentation

Our Acton team are committed to managing our works and mitigating any impacts. Examples of measures we currently have in place include:

  • Hoarding along our site boundary

  • Using specialist equipment which helps reduce vibration in the area

  • Restricting movements of vehicles outside of working hours

  • Keeping within the noise and vibration limits set by LB Ealing.

There are lots of ways to find out what’s happening at our site, you can:

  • Call our 24 hour helpdesk 08000 30 80 80 or email [email protected]

  • Take a moment to read the latest updates on the noticeboards on our hoardings

  • Visit Tideway's Community Information Centre at Carnwath Road, the first Tuesday of the month, 3pm – 7pm. Our team will be able to answer your questions and tell you what's happening on site

  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings

You can also follow our progress and what we're doing in our local communities on Twitter, Instagram and Facebook.

Explore the next sites

Beckton Sewage Treatment works.jpg (1)

Beckton Sewage Treatment Works

London Borough of Newham

6O6A0179 HAMPS 180418.jpg

Hammersmith Pumping Station

London Borough of Hammersmith and Fulham