Deptford Church Street

Site information

This site will be used to intercept the Deptford Storm Relief Sewer combined sewer overflow, divert flows into the Greenwich connection tunnel and to the main tunnel, tackling the problem of sewage overflow into the Deptford Creek.

Deptford Church Street

Shaft excavation is now complete, with secondary lining reinforcement installation works progressing well. The CSO chamber excavation is now deeper than 5m from the roof beam level.

September 2019 Information Sheet

For information on extended working hours

What are our working hours?

Standard working hours are 8am to 6pm Monday-Friday and 8am-1pm Saturday.  Also, there is a 1 hour mobilisation period before and after the Standard Working Hours, plus maintenance periods on Saturday 1-5pm and Sundays 10am-4pm.

 

The last Community Liaison Working Group meeting was held on Thursday 12 September 

12 September 2019 - Community Liaison Working Group Minutes

12 September 2019 - Community Liaison Working Group Presentation

7 May 2019 - Community Liaison Working Group Minutes

7 May 2019 - Community Liaison Working Group Presentation

 

 

Previous minutes are available upon request,  please contact the Tideway Helpdesk on 08000 30 80 80 or email [email protected]

  • Equipment and operations are located away from sensitive receptors

  • The site will be returned to public use as soon as practicable, including potential phasing, allowing partial use

  • A 3.6m high hoarding has been erected on the site boundaries

  • No scheduled lorry movements will take place between 8:30 to 9:15 and 15:00 and 15:45 during school term time

  • All concrete used will be delivered pre-mixed

  • Access/egress into Coffey St will be maintained at all times unless otherwise agreed

  • Vehicle movements outside of standard hours are restricted

  • Pedestrian and vehicular access to St Joseph’s Roman Catholic Primary School via Crossfield St will be maintained at all times; with a segregated pedestrian route to the school

There are lots of ways to find out what’s happening at this site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected]

  • Take a moment to read the latest updates on the noticeboards on our hoardings.

  • Visit Tideway's Community Information Centre at Chambers Wharf open every Wednesday 2pm – 7pm, our team will be able to answer your questions and talk about the work.

  • Email our dedicated Community Relations teams available to answer your questions or meet with you, via [email protected]

  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings.

You can also sign up to receive information updates and newsletters via [email protected].

Submissions to the Council 
Our works will be undertaken with the same controls identified in the Development Consent Order and Code of Construction Practice. We will notify anyone living near the site in advance of any works taking place. We are making a number of submissions to the London Borough of Lewisham as part of the consents we need to secure before starting different phases of work at the Deptford Church Street site. These submissions are available to view on the London Borough of Lewisham's planning portal by searching for 'Thames Tideway Tunnel. Please click here to be redirected. If you are interested on commenting on these submissions, please ensure you respond directly to the London Borough of Lewisham.