Falconbrook Pumping Station is largely an existing Thames Water pumping station site. This site encompasses the pumping station, a disused public convenience and a small area of York Gardens.

Falconbrook Pumping Station

September 2019

Work is progressing well at Falconbrook Pumping Station. We are continuing with piling works to shape our interception chamber that will connect the Pumping Station to our new tunnel. Piles are augered into the ground, a technique that requires an auger drill to excavate a hole before concrete is poured to create the pile. 

We recently completed piling to shape the first 13m of our 42m deep shaft on site. A total of 53 piles were augered into the ground. The next stage for this work is to install a capping beam around the shaft perimeter, a reinforced concrete structure on top of the piles holding them in place. This will require us to break down a number of the concrete piles using either a cutting and break, splitting or wire saw technique. 

September 2019 - Capping Beam Works

What are our working hours?

Standard working hours

08:00 - 18:00 Monday - Friday

08:00 - 13:00 Saturday

Extended working hours

We are currently working extended working hours to complete piling works

07:00 - 19:00 Monday to Friday

A mobilisation period of up to one hour may be required before and after standard working hours. 

There will be a period of 24/7 works, the majority of which will be underground

We hold CLWG drop-in meetings twice a year for our Falconbrook Pumping Station site. 

Our most recent CLWG drop-in meeting for Falconbrook Pumping Station was held in September 2019. The date of the next meeting will be announced soon.

If you have any queries in the meantime, please contact [email protected]

 

  • Advanced tree planting in York Gardens ahead of the start of construction
  • Access to the York Gardens Library and Community Centre and York Gardens Adventure Playground has been maintained
  • No construction traffic access the site through the residential area from Lavender Road
  • Construction traffic access the site via new entry and exit points off York Road
  • Pedestrian access from York Road to York Gardens has been maintained
  • All static machinery and plant is screened or enclosed
  • Hoarding has been erected on the site boundaries
  • The excavated material handling area is enclosed 

There are lots of ways to find out what’s happening at this site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected]
  • Take a moment to read the latest updates on the noticeboards on our hoardings.
  • Email our dedicated Community Relations teams available to answer your questions or meet with you, via [email protected]
  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected].

You can also follow our progress and what we're doing in our local communities on Twitter, Instagram and Facebook

Submissions to the Council
We are making a number of submissions to the London Borough of Wandsworth as part of the consents we need to secure before starting different phases of work at the Falconbrook site. These submissions are available to view on the London Borough of Wandsworth's planning portal. Please click here to be redirected to the portal. If you are interested on commenting on these submissions, please ensure you respond directly to the London Borough of Wandsworth.

Explore the next sites

6O6A1218  CARRR 210318.jpg

Carnwath Road Riverside

London Borough of Hammersmith and Fulham

Cremorne Wharf_181.jpg

Cremorne Wharf Depot

Royal Borough of Kensington and Chelsea