Carnwath Road Riverside

Site information

This site is made up of two parts; a main site (which includes Whiffin Wharf, Hurlingham Wharf, Carnwath Road Industrial Estate and an area of the River Thames foreshore) and a small highways work site.

Carnwath Road Riverside

Rachel, the Tunnel Boring Machine (TBM) has begun her journey towards Acton Pumping Station, where she will resurface next year. 

At the site above ground, the site team have almost completed the installation of the conveyor system and the new muck bin.

For more information, look at the latest CLWG presentation on the tab below.

Our standard working hours are (with a 1-hour mobilisation period before and after these times):

  • Monday – Friday: 8am – 6pm

  • Saturday: 8am – 12 midday

Additionally, we have maintenance periods on the weekend:

  • Saturday: 1 – 5pm

  • Sunday: 10am – 4pm

When we begin tunnelling we will be working 24-hours a day. This will be taking place predominantly underground.

The next Carnwath Road Riverside CLWG will be announced shortly.

You can see the the minutes and presentation from the last CLWG below. If you are interested in finding out more about our community liaison working group please email [email protected]

10 June 2019 - CLWG Presentation

18 February 2019 - CLWG Minutes
18 February 2019 - CLWG Presentation

Our Carnwath Road team are committed to managing our works and mitigating any impacts. Example of measures we currently have in place include:

  • There is an acoustic shed over the tunnel drive shaft 

  • All static machinery and plant are being screened/enclosed

  • Hoarding has been erected on the site boundaries

  • Vehicle movements outside of standard hours are restricted

  • Use of low level directional lighting

  • Set limits to control activities, such as noise (Section 61 approval) from LB Hammersmith & Fulham

There are lots of ways to find out what’s happening at this site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected].

  • Take a moment to read the latest updates on the noticeboards on our hoardings.

  • Visit Tideway's Community Information Centre at Carnwath Road, the first Tuesday of the month, 3pm – 7pm. Our team will be able to answer your questions and talk about the work.

  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings.

You can also follow our progress and what we're doing in our local communities on TwitterInstagram and Facebook.

Submissions to the council
We have been making a number of submissions to the London Borough of Hammersmith and Fulham as part of the consents, as we need to secure before starting different phases of work at Carnwath Road Riverside. These submissions will be available to view on the London Borough of Hammersmith and Fulham’s planning portal. Please click here to be redirected. This includes the submissions for Hammersmith Pumping Station. If you are interested in commenting on these submissions, please ensure you respond directly to the London Borough of Hammersmith and Fulham. The latest Air Quality and Noise reports for Carnwath Road Riverside can be found here.

Explore the next sites

Site Progress DRMST 6O6A1835.jpg

Dormay Street

London Borough of Wandsworth

Falconbrook_506.jpg

Falconbrook Pumping Station

London Borough of Wandsworth