Dormay Street (Wandsworth)

Dormay Street (Wandsworth)


Aerials_Tideway_West_DRMST 283551.jpg

The Dormay Street site comprises land within the Thames Water’s ownership. This includes part of the Frogmore Depot and Causeway Island, as well as the use of a section of The Causeway running down to the junction with Dormay Street and Armoury Way.

This site will be used to connect the existing local combined sewer overflow to the main tunnel. It is also used to drive a long connection tunnel southwards to King George’s Park and northwards to Carnwath Road Riverside, to connect the combined sewer overflows at Dormay Street and King George’s Park to the main tunnel. This long connection tunnel is known as the Frogmore connection tunnel.

Works update

From the beginning of June, we will be strengthening the river walls. This is to protect and secure the river wall prior to the next phase of works. This will take approximately eight weeks to complete. Read More 

On Monday 30 July we will be taking delivery of the main support crane which will be used for our shaft sinking and construction activities. Read More 

Want to know more or get involved?

There are lots of ways to find out what’s happening at this site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected].
  • Take a moment to read the latest updates on the noticeboards on our hoardings.
  • Visit Tideway's Community Information Centre at Carnwath Road, the first Tuesday of the month, 3pm – 7pm. Our team will be able to answer your questions and talk about the work.
  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings.

Site location

Tideway's River Times - West

The latest issue of Tideway's new regular community newsletter, produced especially for our neighbours in the west section of the project. 

River Times WEST - Autumn 2018 

Dormay Street - Site Information

What are our working hours?

Standard working hours are 8am to 6pm Monday-Friday and 8am-1pm Saturday.  Also, there is a 1 hour mobilisation period before and after the Standard Working Hours, plus maintenance periods on Saturday 1-5pm and Sundays 10am-4pm.

There will be approximately nine months of 24-hour working. However, activities will be predominantly below ground

How will we access the site?

An anticipated daily average of eight heavy goods vehicles will access the site for the majority of the construction period. This will rise to approximately 25 heavy goods vehicles per day over an estimated four month period while the Frogmore connection tunnel is excavated.

Dormay Street - How we will minimise disruption

  • Hoarding will be erected along the site boundary
  • Vehicle movements outside of standard hours will be restricted
  • Use of low level directional lighting
  • Set limits to control activities, such as noise (Section 61 approval) from LB Wandsworth

Dormay Street - Community Liaison Working Group

The next Dormay Street and King George's Park CLWG will take place on Thursday 22 November, 7-9pm, at The Brewer's Inn (147 East Hill, Wandsworth, SW18 2QB).

05 July, 2018 Community Liaison Working Group Minutes

05 July, 2018 CLWG Presentation

22 February, 2018 Community Liaison Working Group Minutes

22 February, 2018 CLWG Presentation

 

Our community

Working in the community

Giving back to the community

Education programme

Careers and skills