Hammersmith Pumping Station

Site information

Hammersmith Pumping Station is an existing Thames Water pumping station site. The site covers the pumping station and part of the Fulham Reach development (currently under construction) and minor highway works. The site will be used to intercept the existing Hammersmith Pumping Station combined sewer overflow.

Hammersmith Pumping Station

Following a pause as part of our response to the COVID-19 outbreak, we have resumed some works at our Hammersmith Pumping Station site. We have introduced several additional precautions so that our team can do this work safely to continue building the super sewer.

At our Hammersmith Pumping Station site, the connection tunnel from the site to the point where it will meet the main tunnel, was completed in 2019. Autumn 2019 saw the site complete the secondary lining of the connection tunnel. The first for the whole project! The secondary lining secures and strengthens the tunnel, before the joining the main Super Sewer.

Earlier this year the site team completed the secondary lining of the shaft. Our Hammersmith site are continuing work inside the Interception Chamber.

Road Closure
As we approach the next phase of our works at our Hammersmith Pumping Station site, on Tuesday 26 May, at approximately 06:00, a large crane and lorry will arrive at site.

For more information, look at the latest CLWG presentation on the tab below.

Our standard working hours are (with a 1-hour mobilisation period before and after these times):

  • Monday – Friday: 8am – 6pm

  • Saturday: 8am – 12 midday

Additionally, we have maintenance periods on the weekend:

  • Saturday: 1 – 5pm

  • Sunday: 10am – 4pm.

We will be working 24-hours a day for approximately nine months. This will be taking place predominantly underground as we construct our tunnel.

On average, we have approximately six heavy goods vehicles accessing the site. More up to date information about the vehicle movements can be found within the CLWG presentations.

As a precautionary measure due to the current public health situation, our Community Liaison Working Group meetings are currently postponed.

We’re sorry for any inconvenience this might cause, however please get in touch via our 24-hour Helpdesk on 08000 30 80 80 or email [email protected] if you would like to speak to a member of the team.

 

The next Hammersmith Pumping Station CLWG will be announced shortly.

You can see the minutes and presentation from the last CLWG below. If you are interested in finding out more about out community liaison working group, please email [email protected].

19 November, 2019 - CLWG Minutes
19 November, 2019 - CLWG Presentation

14 May, 2019 - CLWG Minutes
14 May, 2019 - CLWG Presentation

Our Hammersmith team are committed to managing our works and mitigating any impacts. Examples of measures we currently have in place include:

  • The contractor liaising and coordinating with the Fulham Reach Developer regarding community liaison and communications with local residents and stakeholders

  • Hoarding which has been erected along the site boundary

  • The site offices are positioned along the northern boundary of the site to screen Chancellor’s Road from construction activities

  • The use of surface cranes are minimised outside of standard working hours

  • Limits have been set to control activities, such as noise (Section 61 approval) from LB Hammersmith and Fulham

There are lots of ways to find out what's happening at our site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected].

  • Take a moment to read the latest updates on the noticeboards on our hoardings.

  • Visit Tideway's Community Information Centre at Carnwath Road, the first Tuesday of the month, 3pm – 7pm. Our team will be able to answer your questions and talk about the work.

  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings

You can also follow out progress and what we're doing in our local communities on Twitter, Instagram and Facebook.

Submissions to the Council
We have been making a number of submissions to the London Borough of Hammersmith and Fulham as part of the consents, as we need to secure before starting different phases of work at Hammersmith Pumping Station. These submissions will be available to view on the London Borough of Hammersmith and Fulham’s planning portal. Please click here to be redirected. This includes submissions made for Carnwath Road Riverside. If you are interested in commenting on these submissions, please ensure you respond directly to the London Borough of Hammersmith and Fulham.