Hammersmith Pumping Station

Site information

Hammersmith Pumping Station is an existing Thames Water pumping station site. The site covers the pumping station and part of the Fulham Reach development (currently under construction) and minor highway works. The site will be used to intercept the existing Hammersmith Pumping Station combined sewer overflow.

Hammersmith Pumping Station

March 2020

Our number one priority is the health, safety and wellbeing of our employees and the wider public. We are following public health guidance and all non-essential staff who can work from home are doing so. At Hammersmith Pumping Station our site is now temporarily closed.

If you have any questions about this or our site at Hammersmith Pumping Station please get in touch with our helpdesk on 08000 30 80 80 or [email protected]

At our Hammersmith Pumping Station site, the connection tunnel from the site to the point where it will meet the main tunnel, was completed in 2019. Autumn 2019 saw the site complete the secondary lining of the connection tunnel. The first for the whole project! The secondary lining secures and strengthens the tunnel, before the joining the main Super Sewer.

Additionally, the site team have completed the secondary lining of the shaft. Our Hammersmith site are continuing work inside the Interception Chamber.

Piling Update
From Monday 16 March we will begin piling works.

For more information, look at the latest CLWG presentation on the tab below.

Our standard working hours are (with a 1-hour mobilisation period before and after these times):

  • Monday – Friday: 8am – 6pm

  • Saturday: 8am – 12 midday

Additionally, we have maintenance periods on the weekend:

  • Saturday: 1 – 5pm

  • Sunday: 10am – 4pm.

We will be working 24-hours a day for approximately nine months. This will be taking place predominantly underground as we construct our tunnel.

On average, we have approximately six heavy goods vehicles accessing the site. More up to date information about the vehicle movements can be found within the CLWG presentations.

As a precautionary measure due to the current public health situation, our Community Liaison Working Group meetings are currently postponed.

We’re sorry for any inconvenience this might cause, however please get in touch via our 24-hour Helpdesk on 08000 30 80 80 or email [email protected] if you would like to speak to a member of the team.

 

The next Hammersmith Pumping Station CLWG will be announced shortly.

You can see the minutes and presentation from the last CLWG below. If you are interested in finding out more about out community liaison working group, please email [email protected].

19 November, 2019 - CLWG Minutes
19 November, 2019 - CLWG Presentation

14 May, 2019 - CLWG Minutes
14 May, 2019 - CLWG Presentation

Our Hammersmith team are committed to managing our works and mitigating any impacts. Examples of measures we currently have in place include:

  • The contractor liaising and coordinating with the Fulham Reach Developer regarding community liaison and communications with local residents and stakeholders

  • Hoarding which has been erected along the site boundary

  • The site offices are positioned along the northern boundary of the site to screen Chancellor’s Road from construction activities

  • The use of surface cranes are minimised outside of standard working hours

  • Limits have been set to control activities, such as noise (Section 61 approval) from LB Hammersmith and Fulham

There are lots of ways to find out what's happening at our site, you can:

  • Call our 24 hour Tideway Helpdesk 08000 30 80 80 or email [email protected].

  • Take a moment to read the latest updates on the noticeboards on our hoardings.

  • Visit Tideway's Community Information Centre at Carnwath Road, the first Tuesday of the month, 3pm – 7pm. Our team will be able to answer your questions and talk about the work.

  • Join our regular Community Liaison Working Group meetings, to attend the meetings or receive the minutes and presentations from past meetings, email [email protected]. Meeting details will be emailed, published online and on site hoardings

You can also follow out progress and what we're doing in our local communities on Twitter, Instagram and Facebook.

Submissions to the Council
We have been making a number of submissions to the London Borough of Hammersmith and Fulham as part of the consents, as we need to secure before starting different phases of work at Hammersmith Pumping Station. These submissions will be available to view on the London Borough of Hammersmith and Fulham’s planning portal. Please click here to be redirected. This includes submissions made for Carnwath Road Riverside. If you are interested in commenting on these submissions, please ensure you respond directly to the London Borough of Hammersmith and Fulham.

Explore the next sites

ACT_Aerial Banner.jpg

Acton Storm Tanks

London Borough of Ealing

Barn Elms_west_barel-1.png

Barn Elms

London Borough of Wandsworth